ARTHIT Pipeline End Manifold Tie-In Spool Installation
| Date Awarded: |
2008 | ![]() |
| Client: |
PTT Exploration and Production Public Company Limited | |
| Description: |
ARV determined the general condition of the prefabricated spool provided by PTTEP, and the rigging, and prepared an installation engineer analysis and procedures for lifting the spool into its final position. ARV then removed the Subsea pig trap and moved the Z spool into its final position using air bags and vessel lifting frame. The Arthit PLEM end of spool was connected using Hydra tight equipment and found that the other end is unable to align and connect. Finally PTT instructed ARV to demobilize the vessel. Finally PTT instructed ARV to demobilize the vessel. ARV was then chosen to assist with spool recovery and modification works. |
|
| Destination: |
Gulf of Thailand |